Download a printable
PDF version
Download a printable PDF of the images only
Floor Structures & Tranquility Floors
[& insulating them]
There are various structural floors that these floors will be laid on, so as the options for each are different here are some general forms of construction with drawings to help show what should be done. This advice comes from a long history of designing low energy buildings – see the Home Page. Both new [or modern] build and existing buildings are covered. As a general rule, all floors laid on the ground floor must have one (and only one) damp proof membrane in them - somewhere.
(Drawings referred to in the text below are also available here... as an image file)
The issue to be aware of, if a floating floor was not in the building design from the outset, is the height of the door bottoms which will define how much insulation you can lay. [The doors can be shortened slightly if that makes the difference].
- Flooring grade Polystyrene can be bought in many thicknesses, so most required thicknesses can be accommodated. The total height being laid above the concrete is going to be:
- The final floor – 12mm
- The Chipboard – either 18mm or 22mm, the 22 being more rigid
- The insulation – from 20mm to 100mm
- If there is the height available for 100mm of polystyrene so much the better, but lay it in two 50mm staggered layers and preferably tape each layer together. If not, whatever there is space for is good. Cover the concrete with the tight fitting slabs of polystyrene.
- Now lay a 1200 gauge polythene sheet over the polystyrene but lap it up the walls so it makes a sealed moisture proof tray when trapped behind the skirting boards. It is supplied in a 4m width, so if more than one piece is required they must be taped together with the appropriate waterproof tape.
- Next fit the Tongue and groove chipboard floor which is glued to form a single membrane.
- Lay the Tranquility floor and finish it (N.B. follow the detailed instructions on How to lay a Tranquility Floor)
- Fit the architraves around the doors and then the skirtings to complete the room.
First Floors on Joists: see Drawings 3 & 4
As long as the existing floor is level, the Tranquility floor is simply laid on top, but if for some reason you are going back to the joists, simply lay chipboard – it can be 18mm so long as the joists are not more than 450mm between centres or 22mm if wider. So long as the board joints are on top of the joists it doesn’t need to be glued, but if the house is old and the joists irregular it would have to be glued well.
But you still have two options to consider. Do you remove the skirtings and architraves or lay between them?
Ground Floors on Joists: will normally apply to existing buildings.
The underside of the floor must be ventilated or the joists will rot, so there will be air bricks in the outside wall of the house. Such floors usually allow between a good draught and a howling gale to come up through them, so laying a floor is the perfect time to resolve this issue and to insulate it – see Drawing 3. The only direction for the long term price of energy is up, so all floors should be sealed as well as possible against all air leaks and a total draught proof situation can be achieved.
In order to do the job properly, the floor boards will need to be lifted as adding insulation on top of existing timber floor boards (if there were space) would cause them to rot. So there are a number of solutions and options but the golden rules are:
- Either remove all the floor structure and fill the void so you construct a solid floor which then isn’t ventilated or
- Insulate soundly under the floor and put a sealed vapour proof membrane over the insulation and under the new floor.
Filling the Void: see Drawing 5
This requires everything to be removed and the room(s) will look like building sites at their worst. This solution wouldn’t make sense if the depth of the void was too great but up to around 250mm is fine, and starting from bare earth would not be a great idea:
- Remove everything to get back to the solid structure beneath the void.
- Level the bottom following the rules above ‘What to do if the concrete slab is uneven’.
- Determine what depth to build up to before the new floor is laid and follow the guidance above under ‘Ground Floors on Concrete’.
Insulating under the floor: see Drawing 6
- Lift the floor boards and lay some scaffold boards or sheets of chipboard to work off.
- The bottoms of the joists must remain in the air flow along with about ⅓ of the depth to keep them dry. Decide what insulation depth is available and fix battens to the sides of the joists the insulation depth below the top of the joists.
- Cut the insulation you are going to use (polystyrene is best) to fit snugly between the joists and fit it so it is continuous. It must be tight up under the new floor as leaving gaps in a howling gale allows the cold air to move freely under the floor.
- Lay a 1200 gauge plastic membrane across the top of the insulation and joist tops – as above to run up the walls behind the skirting when fitted. This is hugely important for this installation. If more than one sheet is required they must be securely taped together with waterproof tape.
- Now lay the T & G chipboard floor, gluing as above and fixing down with annular ring shank nails securely to the joists. Fixings should be at 150mm centres along the joists but make certain the nails find the joists or there will be a hole through the membrane that isn’t sandwiched between the board and joists.
- Lay the Tranquility floor (N.B. follow the detailed instructions on How to lay a Tranquility Floor) and when finished fix the skirtings through the membrane to the walls. Stainless helical fixings are a wonder as there is very little finishing to do before decoration.